CASE STUDY

ABOVE-GROUND STP INSTALLATION

22nd July 2025

Illustration of a steam radiator with labeled components.

THE  CIRCUMSTANCES 

SEWAGE TREATMENT PLANT

The customer had a Sweage Treatment Plan that served both their property & a holiday cottage

Following a recent storm, a river in close proximity of the customer’s property had burst its banks

RIVER FLOODING

PROPERTY DAMAGE

Due to the river flooding, the downstairs of the holiday cottage was sitting in water

When inspecting the Sewage Treatment Plant, we found root ingress & failed electrical components

STP DAMAGE

Works were recommended & carried out in order to resolve the customer’s issue

WORKS REQUIRED

THE  TIMELINE 

1

FIRST CONTACT

On 22/07, a dedicated Claims Technician contacted the customer to introduce themselves, complete an in-depth triage and explain their options. An appointment was booked to attend the property on 01/08 to complete an investigation.

2

INVESTIGATION

Our engineer attended the customer’s property to investigate on 01/08. All site data was submitted by our engineer and reviewed by the customer’s Claim Technician. A report was produced and submitted for authorisation on 04/08.

3

REPAIR

Authorisation to proceed with the case was provided on 04/09. We attended the customer’s property on 17/09 to complete final investigations ahead of the planned repairs. Recommended repairs were authorised on 30/09. The works started on 08/12 and took 2 weeks to complete.

4

SATISFACTION

The customer’s dedicated Claim Technician called to confirm they were happy with the works completed. The customer was also issued with their 3-Year TankShield Warranty for our repairs.

     OUR  SOLUTION      

Due to flooding following the storm, the Sewage Treatment Plant was found to be completely submerged. As a result the electrical systems were no longer operational.

Our CCTV survey revealed evidence of root ingress through joints within the Sewage Treatment Plant, as well as within the outlet pipework, therefore reducing efficiency.

In order to resolve the customer’s issues, we excavated and installed a new 10PE Sewage Treatment Plant with a pumped outlet.

In order to prevent future flooding, we left the Sewage Treatment Plant out of the ground and built wooden sleepers surrounding this before filling with stone.

Your Engineers did a brilliant job, thank you for all of your help.

Customer